| MISSOURI RIVER |

| Project |
|
| Location |
|
| Contract |
| | Dredge Type: Cutter Suction Dredge
Quantity: 500,000 cubic yards
|
|
| Description |
| |
As a subcontractor, this project involved pumping 500,000 cubic yards of material to create a large bird nesting habitat within the Missouri River. The creation of this island at river mile 777 and the accompanying backwater fish habitat was part of a series of habitat creation projects on the Missouri River. |
|
| |
|
|
| LEWIS & CLARK LAKE |

| Location |
| | Springfield, South Dakota |
|
| Contract |
| | Dredge Type: Cutter Suction Dredge
Dredge: L.W.
Quantity: 1,100,000 cubic yards
|
|
| Description |
| | The 20-inch dredge L.W. completed this project for the U.S. Army Corps of Engineers, Omaha District. The project involved dredging 1,100,000 cubic yards of sand from the Missouri River and using the material to construct a bird habitat island. |
|
| |
|
|
| POOL 8 ISLANDS |

| Project |
|
| Location |
|
| Contract |
| | Dredge Type: Cutter Suction Dredge
|
|
| Description |
| | This project, funded under the Environmental Management Program, involved the creation of four new nesting habitat islands within Pool 8 of the Mississippi River, as well as four later-awarded additional islands. |
|
| |
|
|
| YAZOO BASIN ENHANCEMENT PROJECT |

| Location |
|
| Contract |
| | Dredge Type: Cutter Suction Dredge
Quantity: 1,700,000 cubic yards
|
|
| Description |
| | The Yazoo Basin Enhancement Project 6B involved dredging 1,700,000 cubic yards with beneficial disposal of dredge material within existing agricultural lands. This project was performed to reduce flooding within the
Yazoo
Basin and provide improved crop land for area farmers.
|
|
| |
|
|
| CRYSTAL LAKE |

| Location |
|
| Contract |
| | Dredge Type: Cutter Suction Dredge
Quantity: 1,300,000 cubic yards
|
|
| Description |
| |
This project involved dredging 1,300,000 cubic yards from
Crystal Lake, located in
Hancock County,
IA. The project also included removal, replacement and extension of an existing aeration system, as well as incidental work. |
|
| |
|
|
| LAKE TRAFFORD RESTORATION |

| Location |
|
| Contract |
| | Dredge Type: Cutter Suction Dredge
Dredge: L.W.
Quantity: 4,000,000 cubic yards
|
|
| Description |
| |
This project involved dredging approximately 4,000,000 cubic yards of sediment from
Lake
Trafford, located in
Immokalee,
Florida, using the 20-inch dredge L.W. The project required the dredge material to be pumped 16,000 feet to a confined disposal area. |
|
| |
|
|
| MCCLELLAN-KERR ARKANSAS NAVIGATION SYSTEM |

| Location |
|
| Client |
| | USACE- Little Rock District
|
|
| Contract |
| | Dredge Type: Cutter Suction Dredge
Dredge: Jolly Roger
|
|
| Description |
| | The 20-inch dredge Jolly Roger completed this maintenance dredging contract for the U.S. Army Corps of Engineers, Little Rock District, restoring the Federal Navigation channels on the White and
Arkansas
Rivers to their 9-foot and 12-foot depths.
|
|
| |
|
|
| HOLCIM STE. GENEVIEVE |

| Location |
|
| Contract |
| | Dredge Type: Cutter Suction Dredge
Dredge: Sandpiper
Quantity: 1,000,000 cubic yards
|
|
| Description |
| | The 20-inch dredge Sandpiper excavated 1,000,000 cubic yards of sand and clay for use in the construction of a new barge terminal for Holcim U.S. plant, located in
Bloomsdale,
MO. The material removed from the site was pumped 8,000 feet to a man-made containment area located behind a 130-foot tall dam.
|
|
| |
|