| Location |
|
| Client |
|
| Contract |
| | Dredge Type: Cutter Suction Dredge
Dredge: Illinois
Quantity: 1,250,000 cubic yards
Beach Construction: 16,000 ft
Duration: October - December 2008 |
|
| Description |
| |
This beach renourishment project involved placing approximately 1,250,000 cubic yards of material along Tybee Island beaches in Georgia. Dredged material was pumped from a borrow site located approximately 1.5 miles offshore and placed onto the project areas. Project operations were performed by the cutter suction dredge Illinois. |
|
| |